Public decision
Request for approval of an Order Authorizing Settlement in connection with Harris County and Wadecon, LLC; Projects located in Harris County: (1) Greenhouse Road North Approach Project, Job No. 21/0408; (2) Greenhouse Road 4 Project, Job No. 21/0177; (3) Greenhouse Road 5 Project, Job No. 21/0199; and (4) Telge Road Segment 2 Project, Job No. 21/0431; CAO File Nos. 2023AFF0233, 2023AFF0215, 2022AFF0142, 2023AFF0234.
Harris County Commissioners Court considers approving a legal settlement with road contractor Wadecon, LLC on July 9, 2026.
Harris County Commissioners Court
Public decision
Request that the County Judge execute an amendment to an agreement with The Gordian Group, Inc. in the additional amount of $350,000 for consulting services for job order contracting management system for Harris County for the extended period of August 24, 2026 - April 23, 2027 (210052), Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Harris County may approve a $350,000 extension of its consulting contract with The Gordian Group for job order contracting management through April 2027.
Harris County Commissioners Court
Public decision
Request for approval of renewal of incentive pay policy to use surplus labor budget funds and identified grant funds to pay staff for certification achievement, special job assignments, or grant program involvement effective upon adoption through April 2027.
Harris County renewed a policy to pay staff bonuses for certifications, special assignments, or grant work through April 2027.
Harris County Commissioners Court
Public decision
Request that the County Judge execute an amendment to an agreement with Royal American Services, Inc. in the additional amount of $700,000 to continue services for job order contracting for small and/or large roofing projects for Harris County for the period of May 1, 2026 - April 30, 2027 (220340), MWBE Contracted Goal: 9%.
Harris County may add $700,000 to a roofing contract with Royal American Services, Inc. for county buildings through April 2027.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with SER Construction Partners LLC, in connection with Pine Trails Subdivision Drainage Improvements (Sections 1-2-5-6) - 2018, adding 3 calendar days, with a deduction in the amount of $6,493.36, Job No. 24/0358-01, Mobility Fund, UPIN 19101MF14202, Precinct 2, MWBE Contracted Goal: 26.94%, MWBE Current Participation: 37.91%.
Harris County reviews a contract amendment with SER Construction Partners for Pine Trails drainage work in Precinct 2, adding 3 days and deducting $6,493.36.
Harris County Commissioners Court
Public decision
Request for approval of change in contract No. 8 with LASS Engineering and Construction, LLC, for general drainage system repairs - south, resulting in an addition of $640,502 to the contract amount (Project ID Z100-00-00-X334, Job No. 25/0003, Countywide, MWBE Contracted Goal: 18.58%, MWBE Current Participation: 100%).
Contract amendment adding $640,502 to LASS Engineering for south Harris County drainage repairs; 100% MWBE participation.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding 200 calendar days, with no change in the amount, Job No. 22/0461-13, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 40.15%.
Commissioners Court considers adding 200 days to a road contract for West Gulf Bank Road in Precinct 2, with no cost change.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution System - Berwyn Drive - 2024, with a deduction in the amount of $241,293.11, Job No. 24/0430-2, UPIN 24289MF3JQ01, Precinct 2, MWBE Contracted Goal: 22.74%, MWBE Current Participation: 100%.
Harris County reviews a contract reduction of $241,293.11 for the Berwyn Drive water distribution system project in Precinct 2.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Hayden Paving, Inc., in connection with BS2N Hardy/Aldine - 2024, with an addition in the amount of $1,208,508.65, Job No. 25/0017-1, UPIN 24102MF3B401, Precinct 2, MWBE Contracted Goal: 21.66%, MWBE Current Participation: 99.32%.
Harris County will vote July 9, 2026 on a $1.2M contract addition for Hardy/Aldine road improvements under the BS2N Community Program.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Environmental Allies, Inc., in connection with Detention Basin Enhancement Program - Goforth - 2021, adding 40 calendar days, with an addition in the amount of $20,365.43, Job No. 24/0059-2, UPIN 21103N306330001, Precinct 3, MWBE Contracted Goal: 29.01%, MWBE Current Participation: 14.78%.
Harris County will vote July 9, 2026 on a contract change adding 40 days and $20,365 to a flood mitigation pump station project at Goforth Park.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with R Miranda Trucking and Construction LLC, in connection with Creel Country Estates Subdivision Drainage Improvements 2018, adding 81 calendar days, with a deduction in the amount of $25,222.87, Job No. 24/0406-02, UPIN 19102MF12T01, Precinct 2, MWBE Contracted Goal: 24.18%, MWBE Current Participation: 99.96%.
Harris County reviews a contract amendment for Creel Country Estates drainage work, adding 81 days and cutting costs by $25,222.87.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Spawglass Construction Corp. in connection with Challenger 7 Improvements, adding 215 calendar days, with an addition in the amount of $65,865.78, Job No. 24/0264-4, UPIN 20101MF1F101, Precinct 2, MWBE Contracted Goal: 41%, MWBE Current Participation: 42.85%.
Harris County Commissioners Court considers a contract extension and $65,865.78 increase for Challenger 7 Memorial Park improvements on July 9, 2026.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with SER Construction Partners LLC, in connection with Pine Trails Subdivision Drainage Improvements (Sections 1-2-5-6) - 2018, adding 3 calendar days, with a deduction in the amount of $6,493.36, Job No. 24/0358-01, Mobility Fund, UPIN 19101MF14202, Precinct 2, MWBE Contracted Goal: 26.94%, MWBE Current Participation: 37.91%.
Contract amendment for Pine Trails drainage work in Precinct 2 adds 3 days and deducts $6,493.36.
Harris County Commissioners Court
Public decision
Request for approval of change in contract No. 1 with Arrowstone Contracting, LLC, for the Lauder Stormwater Detention Basin - Compartment 2 (Greens Bayou Watershed, Project ID P500-06-00-E007, Job No. 25/0394, Precinct 2, MWBE Contracted Goal: 31.50%).
Harris County seeks approval of a contract amendment with Arrowstone Contracting for the Lauder Stormwater Detention Basin in Precinct 2.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with CE Barker Ltd., in connection with Barwood Subdivision Drainage Improvements - 2018, with an addition in the amount of $261,096.64, Job No. 25/0227-01, UPIN 19103MF12H01, Precinct 3, MWBE Contracted Goal: 22.07%, MWBE Current Participation: 9.80%.
Commissioners Court considers adding $261,096.64 to CE Barker Ltd.'s contract for Barwood Subdivision drainage improvements in Precinct 3.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with GLM Contracting, Inc., in connection with On-Call - General Civil, Precinct 3 - 2021, with no change in the contract amount, Job No. 22/0019-1, UPIN 22103MF2E401, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 31.76%.
Harris County will vote on a contract amendment with GLM Contracting for Precinct 3 civil construction work, with no change to the contract amount.
Harris County Commissioners Court
Public decision
Request for approval of change in contract No. 6 with Lecon, Inc., for major maintenance of Cypress Creek and Tributaries, Batch 4, adding 21 calendar days (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-X110, Job No. 23/0237, Precinct 3, MWBE Contracted Goal: 21%, MWBE Current Participation: 18.10%).
Harris County Commissioners Court votes July 9, 2026 on a 21-day schedule extension for Cypress Creek flood channel maintenance in Precinct 3.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with MB Western Construction Co., in connection with Houmont Park Subdivision Drainage Improvements - 2018 (P117-00-00), adding 273 calendar days, with an addition in the amount of $53,552.04, Job No. 25/0142-1, HC Commercial Paper Fund, UPIN 19101MF14G01-2, Precinct 1, MWBE Contracted Goal: 27.17%, MWBE Current Participation: 100%.
Harris County seeks approval of a contract amendment with MB Western Construction Co. for Houmont Park drainage improvements in Precinct 1.
Harris County Commissioners Court
Public decision
Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $351,403.24, Job No. 24/0139-7, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
Harris County Commissioners Court considers a $351,403.24 contract change order with Precise Services, Inc. for the Connorvale Development stormwater project in
Harris County Commissioners Court