Request for approval of change in contract No. 1 with ERC Environmental & Construction Services, Inc., for the renovation of the distribution center at the Michael Talbot Service Center, adding 90 calendar days and resulting in an addition of $253,568 to the contract amount (Project ID Z100-00-00-X360, Job No. 26/0067, Precinct 1, MWBE Contracted Goal: 12.42%). | Community Exchange
PolicyCountyOur Government
Request for approval of change in contract No. 1 with ERC Environmental & Construction Services, Inc., for the renovation of the distribution center at the Michael Talbot Service Center, adding 90 calendar days and resulting in an addition of $253,568 to the contract amount (Project ID Z100-00-00-X360, Job No. 26/0067, Precinct 1, MWBE Contracted Goal: 12.42%).
Contract amendment adds 90 days and $253,568 for renovations at the Michael Talbot Service Center distribution center in Precinct 1.
Harris County Commissioners Court is reviewing a contract change with ERC Environmental & Construction Services, Inc. The amendment adds 90 calendar days and $253,568 to the original contract for renovations at the Michael Talbot Service Center distribution center in Precinct 1. The item was introduced on September 3, 2026.
A county building used to distribute services in Precinct 1 is being renovated. A contract change would add time and cost to that project, which is paid with public funds.