Skip to main content
Ask a question.
Tell us what you are looking for in Houston…
Ask

We will show what we know and where it came from.

Request for approval of six (6) Community Development Block Grant Entitlement (CDBG-EN) funded first amendments to agreements with 1) Harris County Precinct 3 total allocation of $1,062,292 for the Runneburg Estates Road Improvements project; 2) Harris County Water Control and Improvement District No. 21 total allocation of $559,762 for the Drinking Water Pump Station Improvements project; 3) Harris County Precinct 2 total allocation of $1,197,114 for the Cheswick Drive Water Distribution project; 4) Harris County Water Control and Improvement District No. 74 total allocation of $635,669 for the Sanitary Sewer Improvements project; 5) Sheldon Road Municipal Utility District total allocation of $799,189 for the Water Line Improvements project; 6) Sunbelt Fresh Water Supply District total allocation of $876,383 for the Oak Glen Water Line Replacement, Phase 2 project. | Community Exchange