Request for approval to correct the amount and the CPI-W escalation summary for Yellowstone Landscape - Central, Inc. from $490,022 (as approved) to $771,682 (corrected) for mowing and maintenance of various parks in the North Zone for Precinct 2 for the period of September 1, 2026 - August 31, 2027, in connection with a renewal option approved by Commissioners Court on June 11, 2026 (230221), MWBE Contracted Goal: 15%, MWBE Current Participation: 12.17%. | Community Exchange
PolicyCountyOur Government
Request for approval to correct the amount and the CPI-W escalation summary for Yellowstone Landscape - Central, Inc. from $490,022 (as approved) to $771,682 (corrected) for mowing and maintenance of various parks in the North Zone for Precinct 2 for the period of September 1, 2026 - August 31, 2027, in connection with a renewal option approved by Commissioners Court on June 11, 2026 (230221), MWBE Contracted Goal: 15%, MWBE Current Participation: 12.17%.
Harris County seeks approval to correct a parks maintenance contract amount from $490,022 to $771,682 for Precinct 2 North Zone parks.
Harris County Commissioners Court is being asked to fix a mistake in a parks maintenance contract. The approved amount of $490,022 was wrong. The correct amount is $771,682, based on an updated cost-of-living calculation. The contract pays Yellowstone Landscape – Central, Inc. to mow and maintain parks in the North Zone of Precinct 2 from September 1, 2026 through August 31, 2027. The item goes before the Court on July 9, 2026. Contact Summer.Turner@pur.hctx.net with questions.
Parks in Precinct 2's North Zone are maintained under this contract. A math error lowered the approved payment amount. This vote corrects the number so the contractor can be paid the right amount for mowing and upkeep.