Request for approval of change in contract No. 7 with Allgood Construction Co Inc., for the excavation of Inwood Forest Stormwater Detention Basin, adding 32 calendar days (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWBE Contracted Goal: 37%, MWBE Current Participation: 44.35%). | Community Exchange
PolicyCountyOur Environment
Request for approval of change in contract No. 7 with Allgood Construction Co Inc., for the excavation of Inwood Forest Stormwater Detention Basin, adding 32 calendar days (White Oak Bayou Watershed, Bond ID C-59, Project ID E500-21-00-E002, Job No. 22/0384, Precinct 1, MWBE Contracted Goal: 37%, MWBE Current Participation: 44.35%).
Contract amendment adding 32 days to excavation work at Inwood Forest Stormwater Detention Basin in Precinct 1.
Harris County Commissioners Court is considering a seventh change to a contract with Allgood Construction Co Inc. The change covers excavation work at the Inwood Forest Stormwater Detention Basin in the White Oak Bayou Watershed, Precinct 1. It would add 32 calendar days to the project timeline. The contractor's current minority and women-owned business participation is 44.35%, exceeding the 37% contracted goal.
This project involves a stormwater detention basin near Inwood Forest. Changes to the timeline could affect when flood-related construction is completed in the White Oak Bayou Watershed area of Precinct 1.