Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of BS2N Hardy/Aldine - 2024, with a deduction in the amount of $541,059.22, Job No. 25/0017-2, UPIN 24102MF3B401, Precinct 2, MWBE Contracted Goal: 21.66%, MWBE Current Participation: 95.05%. | Community Exchange
PolicyCountyOur Government
Request for approval of a change in contract with Hayden Paving, Inc., in connection with final construction of BS2N Hardy/Aldine - 2024, with a deduction in the amount of $541,059.22, Job No. 25/0017-2, UPIN 24102MF3B401, Precinct 2, MWBE Contracted Goal: 21.66%, MWBE Current Participation: 95.05%.
Commissioners Court reviews a $541,059.22 contract reduction with Hayden Paving for the BS2N Hardy/Aldine 2024 construction project in Precinct 2.
Harris County Commissioners Court is reviewing a contract amendment with Hayden Paving, Inc. for final construction work on the BS2N Hardy/Aldine - 2024 project in Precinct 2. The change reduces the contract by $541,059.22. The project set a Minority and Women-Owned Business goal of 21.66%; current participation has reached 95.05%. The item was introduced on August 13, 2026.
This contract change affects a road construction project in Precinct 2. The final contract amount is being reduced by over $541,000, which changes how much the county pays for completed work near Hardy/Aldine.